Free schedule of values template for Excel, in the G703 layout
A schedule of values workbook with the G703 columns set up as formulas. Type your lines and the totals follow.
Download the schedule of values template
One .xlsx in the G703 layout, formulas in place. It downloads straight away, with no email.
Download the templateOr build it online
Paste or type your lines in the free builder. It adds up Column C and bills against it each month. No account.
Build it online- Built for Excel and Google Sheets, no macros
- Styled after the AIA G703, not affiliated with the AIA
- Free, no email, no card
A schedule of values template is a spreadsheet that splits a contract sum into line items, one row each, so every month’s billing is measured against the same list. This one is laid out like a G703 continuation sheet: you type the item, the description and the scheduled value, and the totals, the percent complete and the balance to finish are formulas.
What a schedule of values is
A schedule of values, or SOV, is the contract sum broken into line items. Each line has a description and a scheduled value, which is its share of the contract. Every pay application after that bills against those lines: how much of each was done before, how much this month, and how much is left.
On AIA-style paperwork the schedule of values is Columns A, B and C of the G703 continuation sheet. The billing sits in the columns beside it, on the same rows. The certificate on top is the G702; how the two fit together is in G702 vs G703.
How to build a schedule of values
- Start from the contract sum. The scheduled values have to add up to it exactly, so write the total down first.
- Break the work into lines a reviewer can check on site. Split the job by trade or CSI division, and split a large trade again by phase, by area, or into labor and material.
- Number the lines. Column A is the item number: 1, 2, 3, or the CSI MasterFormat code for the work.
- Give each line its value. Column C is what that line is worth. Put the money where the work is. A schedule that prices the early lines above their worth is front-loading, and reviewers look for it.
- Check the total. Column C has to total the contract sum. Type the contract sum into Line 1 on the G702 Summary sheet, and the check row under Line 9 reads Ties when the schedule adds up to it and shows the difference when it does not.
- Get it approved before the first pay application. The GC or owner reviews the schedule, and every later application is checked against the approved version.
Here is a schedule of values for a $200,000 site-work contract, four lines:
| A · Item no. | B · Description of work | C · Scheduled value |
|---|---|---|
| 1 | Mobilization | 20,000 |
| 2 | Earthwork | 80,000 |
| 3 | Utilities | 60,000 |
| 4 | Paving | 40,000 |
| Total | 200,000 |
The same job is billed through a period, line by line, in the worked schedule of values example.
How the schedule of values becomes the G703
The schedule is typed once. After that, each pay application fills in the billing columns on the same rows. These are the columns of a G703 and what goes in each:
| Column | What it holds | Rule |
|---|---|---|
| A · Item no. | The line number or CSI code | Typed once |
| B · Description of work | What the line covers | Typed once |
| C · Scheduled value | The line’s share of the contract | Sum of C = G702 Line 3 |
| D · From previous application | Work billed on earlier applications | Last month’s D + E; 0 on the first |
| E · This period | Work completed this period | Typed each period |
| F · Materials presently stored | Material stored, not in D or E | Typed each period |
| G · Total completed and stored | Billed to date on the line | D + E + F; sum of G = G702 Line 4 |
| % (no letter) | Percent complete | G ÷ C |
| H · Balance to finish | What is left on the line | C − G |
The AIA form has one more column, I, for retainage. It is used only where retainage varies line by line. The workbook works retainage out on the summary sheet from one rate instead.
Two totals carry to the certificate. The Column C total is G702 Line 3, the contract sum to date. The Column G total is Line 4, total completed and stored to date. On the first application Column D is zero on every line, because nothing has been billed before. What to type each month is in how to fill out a G702 and G703.
What you download
- One .xlsx with three sheets. A Read me, the G703 Schedule sheet, and a G702 Summary sheet that turns the schedule into the payment due once you bill.
- The G703 Schedule sheet is the schedule of values. Type Columns A, B and C in the shaded cells. It has 15 blank rows, and the Read me shows how to add more.
- To send the schedule for approval, leave Columns D, E and F empty. Column C totals at the bottom.
It is the same file as the free G702/G703 Excel template, so the schedule you get approved is the sheet you bill on. It is not the AIA form, and PayAppCheck is not affiliated with the AIA. It is an independently built workbook with the same columns and arithmetic.
When the schedule of values changes
After approval, a scheduled value changes only through a change order. An approved change order is added as its own line at the bottom of the schedule, or adjusts the line it changes. G702 Line 2, net change by change orders, moves by the same amount, so Column C still totals Line 3. The free change order form has a log that totals Line 2.
From the schedule to the first pay app
When the schedule is approved, copy the item numbers, descriptions and scheduled values out of the spreadsheet and paste them into the free G702/G703 builder. It reads the lines, totals Column C, and you type this period’s work in Column E. It checks that the G703 ties to the G702 and downloads the pay app as a PDF or an Excel file. No account is needed. If your GC wants to see a draft before the formal application, send a pencil requisition first.
Questions people ask
Is this schedule of values template free?
Yes. The Excel file downloads straight from this page, with no email and no account. There is no trial, no card, and no limit on how you use it, including on commercial projects.
Is a schedule of values the same as a G703?
The schedule of values is the list of line items and their scheduled values: Columns A, B and C of a G703 continuation sheet. The G703 is that list plus the billing columns: work from previous applications, work this period, materials stored, the total to date and the balance to finish. So a G703 is the schedule of values with the billing on it.
What does a schedule of values have to add up to?
The contract sum. On a pay application the Column C total has to equal G702 Line 3, the contract sum to date, which is the original contract sum plus approved change orders. The workbook has a check row that reads Ties when the two agree and shows the difference when they do not.
How many line items should a schedule of values have?
Enough that a reviewer can check the percent complete on each line against work they can see on site. Break the job down by trade or CSI division, and split a large trade by phase, by area, or into labor and material. The template has 15 blank rows, and its Read me sheet shows how to add more.
Can I change the schedule of values after it is approved?
Only through a change order. An approved change order is added as its own line or adjusts the line it changes, and G702 Line 2 moves by the same amount, so Column C still totals Line 3.
Is this the official AIA G703?
No. It is an independently built workbook with the same columns and arithmetic as a G703 continuation sheet. PayAppCheck is not affiliated with the AIA. If your contract requires the official document, buy it from AIA Contract Documents.
Paste your schedule of values into the free builder and bill against it.
Make a pay app