Georgia lien waiver forms: fill in and download the PDF

Pick the form, fill in the blanks and download the Georgia statutory text as a PDF. Free, no account.

Waiver and Release of Lien and Payment Bond Rights upon Interim Payment (O.C.G.A. 44-14-366(d)). Send it with each progress pay app. It releases work through the date you enter and keeps retainage.
Free, no account. Nothing you type is stored.
We are software, not legal or tax advisors. Verify against your state statute and your accountant.

Published · 4 min read · By Ludvig Bergerud, builder of PayAppCheck

Georgia prescribes 2 statutory lien waiver forms (Official Code of Georgia Annotated section 44-14-366). This page lists each one, when a subcontractor signs it, what the statute requires on the page and the blanks it has, with a form that fills the statutory text with your figures and downloads the PDF.

The forms the statute prescribes

Waiver and Release of Lien and Payment Bond Rights upon Interim Payment (O.C.G.A. 44-14-366(d)). Send it with each progress pay app. It releases work through the date you enter and keeps retainage.

Waiver and Release of Lien and Payment Bond Rights upon Final Payment (O.C.G.A. 44-14-366(e)). Send it with the final pay app.

What Official Code of Georgia Annotated section 44-14-366 requires

Two forms: interim payment (subsection d) and final payment (subsection e). Each must be in at least 12 point type; capitals and bold are no longer required.

The waiver binds the claimant on the earliest of actual payment, a separate written acknowledgment of payment, or 90 days after signing, unless an affidavit of nonpayment is filed inside those 90 days (subsection g).

Because of the 90 day rule there is no separate unconditional form. This tool prints each form as a conditional waiver.

A blank left empty does not invalidate the form as long as the subject of the release can reasonably be determined.

The blanks each form has

Waiver and Release of Lien and Payment Bond Rights upon Interim Payment: County, Customer (who you contracted with), Work or materials you furnish, Project, City, Owner, Property description, Payment amount, Through date, Date signed, Claimant (your company), Title of the person signing, Address.

Waiver and Release of Lien and Payment Bond Rights upon Final Payment: County, Customer (who you contracted with), Work or materials you furnish, Project, City, Owner, Property description, Payment amount, Date signed, Claimant (your company), Title of the person signing, Address.

Fill it from your pay app

Build the pay app in the free builder, and at the end of the form press Make the statutory waiver. Your company, the owner or GC, the project, the period to and the current payment due come over from the G702 into the form, you pick the state and the form, and Send to your GC attaches the waiver to the pay app it belongs to.

We are software, not legal or tax advisors. Verify against your state statute and your accountant.

Build the pay app the waiver goes with, free, and download both.

Make a pay app